SAICA PM 11
PAPER MILL AT PARTINGTON (MANCHESTER)
Progress meeting

Lenntech

25.02.2011



pdf with Planning
TO DO list    Copies                               



Attendance:
Lenntech    ---    ----
Rolf de Boer
Jasper Elgersma
Huite Jan Hak
Andrea Tancredi
Chris Koopman
Maria Baldonedo       


To discuss   

Check progress on skids building:
-    RO1&2 feed
-    CIP skid
-    Air blower
-    RO3 feed
Program the transport of skids to Westra
Confirm Lorivan delivery at Westra
Confirm Sender delivery of 2 RO’s skids
Confirm BEL’s delivery

Brewchem’s offer
-    can we send the PO?
-    Can they fill in the documentation?

Functional description
-    First issue ready to be sent?   

Conclusions    Action by:

Call brewchem to ask for the erection quote    Maria
Chris sends updated drawings to Westra    Chris/ Huite
Update GA and layout with updated drawings from SAICA    Chris
Westra:
-    Ask how do they plan to do the pressure test
-    Tell them the planning so they can organize the work (see below)
-    Shipment of RO1&2 + RO3 feed on the 9th of March
-    Lorivan delivery on the 4th of March    Huite
Building:

-    RO1&2 feed: Wiring left        To be done by 9th March
-    RO3 feed:      Wiring left        To be done by 9th March
-    CIP:               Wiring left
-    Air blower:     Done

Ship RO1&2 feed + RO3 Feed to Westra on 9th of March (if wiring is not finished it will be done together  with the high pressure one at Westra)

Delivery of RO1&2 skid: Friday 25th Feb
Delivery of RO3 skid: Friday 4th Feb.

Start preparing the PVC piping and holes in the skid.

BEL delivers latest the 18th March: Start building

RO1&2 ready: 30th March
Ship RO1&2 to Westra: 1st April

RO3 ready: 12th March
Ship RO3 to Westra: 15th March

One month to:
-     finish building at Westra
-    Wire
-    Pressure tests
-    Pack

Delivery on site: 15th May
Rolf/ Huite/ Martin
Forbes delivery from their warehouse to site: 21st March

Prepare the shipment (done by Lenntech) on 14th March    Andrea/ Maria

EDI check valve:
-    Check if there is a check valve in the product line before the connection with the by-pass
-    Draw it in the P&ID    Marco/ Chris

Please check the following points. They are left in the TO DO list. If they are done, please mark them as done in the list.
Thanks!   
Check stock Throttle valves for pneumatics. Order at Festo
Huite

Do drain valves in the aricon dosing tanks    Martin/ Rolf
Check delivery of actuators for ball valves    Rolf
Brackets form VDL missing    Huite


PROJECT:

Lenntech

TITLE:

SAICA PM 11

PAPER MILL AT PARTINGTON (MANCHESTER)

Progress meeting

LOCATION

Lenntech

DATE

25.02.2011

ATTACHEMENTS:

pdf with Planning

TO DO list

Copies

Attendance:

Lenntech

---

----

Rolf de Boer

Jasper Elgersma

Huite Jan Hak

Andrea Tancredi

Chris Koopman

Maria Baldonedo

To discuss

Check progress on skids building:

- RO1&2 feed

- CIP skid

- Air blower

- RO3 feed

Program the transport of skids to Westra

Confirm Lorivan delivery at Westra

Confirm Sender delivery of 2 RO’s skids

Confirm BEL’s delivery

 

Brewchem’s offer

- can we send the PO?

- Can they fill in the documentation?

Functional description

- First issue ready to be sent?

Conclusions

Action by:

Call brewchem to ask for the erection quote

Maria

Chris sends updated drawings to Westra

Chris/ Huite

Update GA and layout with updated drawings from SAICA

Chris

Westra:

- Ask how do they plan to do the pressure test

- Tell them the planning so they can organize the work (see below)

- Shipment of RO1&2 + RO3 feed on the 9th of March

- Lorivan delivery on the 4th of March

Huite

Building:

- RO1&2 feed: Wiring left To be done by 9th March

- RO3 feed: Wiring left To be done by 9th March

- CIP: Wiring left

- Air blower: Done

Ship RO1&2 feed + RO3 Feed to Westra on 9th of March (if wiring is not finished it will be done together with the high pressure one at Westra)

Delivery of RO1&2 skid: Friday 25th Feb

Delivery of RO3 skid: Friday 4th Feb.

Start preparing the PVC piping and holes in the skid.

BEL delivers latest the 18th March: Start building

RO1&2 ready: 30th March

Ship RO1&2 to Westra: 1st April

RO3 ready: 12th March

Ship RO3 to Westra: 15th March

One month to:

- finish building at Westra

- Wire

- Pressure tests

- Pack

Delivery on site: 15th May

Rolf/ Huite/ Martin

Forbes delivery from their warehouse to site: 21st March

Prepare the shipment (done by Lenntech) on 14th March

Andrea/ Maria

EDI check valve:

- Check if there is a check valve in the product line before the connection with the by-pass

- Draw it in the P&ID

Marco/ Chris

Please check the following points. They are left in the TO DO list. If they are done, please mark them as done in the list.

Thanks!

Check stock Throttle valves for pneumatics. Order at Festo

Huite

Do drain valves in the aricon dosing tanks

Martin/ Rolf

Check delivery of actuators for ball valves

Rolf

Brackets form VDL missing

Huite