SAICA PM 11
PAPER MILL AT PARTINGTON (MANCHESTER)
Progress meeting
Lenntech
25.02.2011
pdf with Planning
TO DO list Copies
Attendance:
Lenntech --- ----
Rolf de Boer
Jasper Elgersma
Huite Jan Hak
Andrea Tancredi
Chris Koopman
Maria Baldonedo
To discuss
Check progress on skids building:
- RO1&2 feed
- CIP skid
- Air blower
- RO3 feed
Program the transport of skids to Westra
Confirm Lorivan delivery at Westra
Confirm Sender delivery of 2 RO’s skids
Confirm BEL’s delivery
Brewchem’s offer
- can we send the PO?
- Can they fill in the documentation?
Functional description
- First issue ready to be sent?
Conclusions Action by:
Call brewchem to ask for the erection quote Maria
Chris sends updated drawings to Westra Chris/ Huite
Update GA and layout with updated drawings from SAICA Chris
Westra:
- Ask how do they plan to do the pressure test
- Tell them the planning so they can organize the work (see below)
- Shipment of RO1&2 + RO3 feed on the 9th of March
- Lorivan delivery on the 4th of March Huite
Building:
- RO1&2 feed: Wiring left To be done by 9th March
- RO3 feed: Wiring left To be done by 9th March
- CIP: Wiring left
- Air blower: Done
Ship RO1&2 feed + RO3 Feed to Westra on 9th of March (if wiring is not finished it will be done together with the high pressure one at Westra)
Delivery of RO1&2 skid: Friday 25th Feb
Delivery of RO3 skid: Friday 4th Feb.
Start preparing the PVC piping and holes in the skid.
BEL delivers latest the 18th March: Start building
RO1&2 ready: 30th March
Ship RO1&2 to Westra: 1st April
RO3 ready: 12th March
Ship RO3 to Westra: 15th March
One month to:
- finish building at Westra
- Wire
- Pressure tests
- Pack
Delivery on site: 15th May
Rolf/ Huite/ Martin
Forbes delivery from their warehouse to site: 21st March
Prepare the shipment (done by Lenntech) on 14th March Andrea/ Maria
EDI check valve:
- Check if there is a check valve in the product line before the connection with the by-pass
- Draw it in the P&ID Marco/ Chris
Please check the following points. They are left in the TO DO list. If they are done, please mark them as done in the list.
Thanks!
Check stock Throttle valves for pneumatics. Order at Festo
Huite
Do drain valves in the aricon dosing tanks Martin/ Rolf
Check delivery of actuators for ball valves Rolf
Brackets form VDL missing Huite
Lenntech |
| |||||||||||||
|
| SAICA PM 11PAPER MILL AT PARTINGTON (MANCHESTER) Progress meeting
| |||||||||||||
Lenntech | ||||||||||||||
25.02.2011 | ||||||||||||||
pdf with Planning TO DO list | Copies |
|
|
|
|
|
|
|
| |||||
|
|
|
|
|
|
|
|
| |||||||
Attendance:
| Lenntech | --- | ---- |
| Rolf de Boer Jasper Elgersma Huite Jan Hak Andrea Tancredi Chris Koopman Maria Baldonedo |
|
|
| To discuss |
|
|
|
|
| Check progress on skids building: - RO1&2 feed - CIP skid - Air blower - RO3 feed Program the transport of skids to Westra Confirm Lorivan delivery at Westra Confirm Sender delivery of 2 RO’s skids Confirm BEL’s delivery
Brewchem’s offer - can we send the PO? - Can they fill in the documentation?
Functional description - First issue ready to be sent?
|
|
|
|
|
| Conclusions | Action by: |
|
|
|
| Call brewchem to ask for the erection quote | Maria |
| Chris sends updated drawings to Westra | Chris/ Huite |
| Update GA and layout with updated drawings from SAICA | Chris |
| Westra: - Ask how do they plan to do the pressure test - Tell them the planning so they can organize the work (see below) - Shipment of RO1&2 + RO3 feed on the 9th of March - Lorivan delivery on the 4th of March | Huite |
| Building:
- - - CIP: Wiring left - Air blower: Done
Ship RO1&2 feed + RO3 Feed to Westra on 9th of March (if wiring is not finished it will be done together with the high pressure one at Westra)
Delivery of RO1&2 skid: Friday 25th Feb Delivery of RO3 skid: Friday 4th Feb.
Start preparing the PVC piping and holes in the skid.
BEL delivers latest the 18th March: Start building
RO1&2 ready: 30th March Ship RO1&2 to Westra: 1st April
RO3 ready: 12th March Ship RO3 to Westra: 15th March
One month to: - finish building at Westra - Wire - Pressure tests - Pack
Delivery on site: 15th May
| Rolf/ Huite/ Martin |
| Forbes delivery from their warehouse to site: 21st March
Prepare the shipment (done by Lenntech) on 14th March | Andrea/ Maria |
|
|
|
| EDI check valve: - Check if there is a check valve in the product line before the connection with the by-pass - Draw it in the P&ID | Marco/ Chris |
|
|
|
| Please check the following points. They are left in the TO DO list. If they are done, please mark them as done in the list. Thanks! |
|
| Check stock Throttle valves for pneumatics. Order at Festo
| Huite
|
| Do drain valves in the aricon dosing tanks | Martin/ Rolf |
| Check delivery of actuators for ball valves | Rolf |
| Brackets form VDL missing | Huite |